Project overview
- Project: The recovery of explosive ordnance in Küstrin-Kietz
- Site: The 35,000 m² construction site of the new bridge
- Data & facts: 1000 boreholes for deep foundations and ordnance clearance
Project background
We were tasked with clearing the construction site for the new Oder bridge connecting Küstrin-Kietz and Kostrzyn of explosive ordnance during the construction work. The construction site surrounding the bridge was cleared of explosive ordnance and munition remnants.
The total area covered was 35,000 m². The bridge will be built with deep foundations. We drilled the 1000 boreholes required for construction work to proceed without risk.